S
Silene
Hi,
I have a task that was done by 3 resources on overtime (Thursday after
working hours and Friday that is a nonworking day). I am not sure where do
change the calendar to make this work done at this times.
Also, if I give a 1 day task to 1 resource at 150%, it means he work
overtime?
Thanks,
Silene
I have a task that was done by 3 resources on overtime (Thursday after
working hours and Friday that is a nonworking day). I am not sure where do
change the calendar to make this work done at this times.
Also, if I give a 1 day task to 1 resource at 150%, it means he work
overtime?
Thanks,
Silene