M
MD
What are some of the best strategies for determining whether to have
employees on a project work OT or not?
Also, where in Project (views/tables) should I look to see what effect
adding OT on a particular task would have on (1) the duration and the (2)
cost?
I've been viewing the Gantt Chart and splitting the window to see the task
form. If I change the form to display the Resource Work, then increase the
Ovt Work value, I can see the duration update. (the task is fixed work)
I've also tried viewing the Task Usage on top (with the Cost table) and the
task form on bottom. This seems to work well but wondered if there's a
better way to do/see this. How do all you MVP's handle this?
employees on a project work OT or not?
Also, where in Project (views/tables) should I look to see what effect
adding OT on a particular task would have on (1) the duration and the (2)
cost?
I've been viewing the Gantt Chart and splitting the window to see the task
form. If I change the form to display the Resource Work, then increase the
Ovt Work value, I can see the duration update. (the task is fixed work)
I've also tried viewing the Task Usage on top (with the Cost table) and the
task form on bottom. This seems to work well but wondered if there's a
better way to do/see this. How do all you MVP's handle this?