Hello, client is using Server 2003 and has several versions of the
same project in Project Server. The reason was due to lack of
training on the project from the start. If I were to clean up PWA,
would I first need to close all open tasks within Project Pro, choose
to overwrite actuals, save an republish assignments. The reason here
is to complete the Task Assignment.

Then I can go in as the ADMIN, and delete the closed (and no longer
needed project). Would the resource sill have to hide these tasks, or
will they drop off?

or could I just delete the projects that are not needed, the team
member will have to hide their tasks

Thanks

MC
 
D

Dale Howard [MVP]

MC --

Delete the projects that are not needed. When you do so, the task
assignments in those projects will disappear on the View My Tasks page for
each resource assigned to tasks in those projects. Hope this helps.
 
M

mike

MC --

Delete the projects that are not needed.  When you do so, the task
assignments in those projects will disappear on the View My Tasks page for
each resource assigned to tasks in those projects.  Hope this helps.










- Show quoted text -

Thanks Dale !
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top