godrid
Hi,
I found out that the baseline work value in the OLAP data analysis does not
match with that from Project Professional or PWA. I have published the
project again just to make sure but the value still does not match up.
After some investigations, I found out that because the project I am dealing
with has been closed with resource removed from those tasks not started,
somehow the OLAP baseline work data for those tasks without resource shows
0hr. The baseline work from PWA or project professional still shows the
baseline work as it is before the removal of resource. Is this a bug?
Regards
Godrid
I found out that the baseline work value in the OLAP data analysis does not
match with that from Project Professional or PWA. I have published the
project again just to make sure but the value still does not match up.
After some investigations, I found out that because the project I am dealing
with has been closed with resource removed from those tasks not started,
somehow the OLAP baseline work data for those tasks without resource shows
0hr. The baseline work from PWA or project professional still shows the
baseline work as it is before the removal of resource. Is this a bug?
Regards
Godrid