G
godrid
Hi,
Is there any best practice on the resource manager role for project server?
Should I setup generic resource for PM to select and then resource manager
replace generic resource with actual work resource under his charge? Do
resource manager normally given edit permission to project plan to assign
resource to the task or he is just restricted to build team permission in PWA?
I would appreciate if you could share your experience of using resource
manager in your implementation.
Regards
Godrid
Is there any best practice on the resource manager role for project server?
Should I setup generic resource for PM to select and then resource manager
replace generic resource with actual work resource under his charge? Do
resource manager normally given edit permission to project plan to assign
resource to the task or he is just restricted to build team permission in PWA?
I would appreciate if you could share your experience of using resource
manager in your implementation.
Regards
Godrid