godrid
Hi,
I have a scenario whereby I need to track the usage of hardware resource
(e.g. Test Machine) which could be used across multiple projects. I would
like to include this hardware resource in my project plan so I could look
have an overall view of any contention of this resource. I setup the resource
as a material resource and assigned it to my project plan. When I check the
view assignments function of my material source in resource center, the start
and finish dates are empty and there is no gantt chart, all I see here is the
project that the resource is assigned to. Is it the correct way to handle
this type of resource?
I would want to show the list of project, task, planned start and end date
for this resource in a view, is there any other way to achieve that?
Regards
Godrid
I have a scenario whereby I need to track the usage of hardware resource
(e.g. Test Machine) which could be used across multiple projects. I would
like to include this hardware resource in my project plan so I could look
have an overall view of any contention of this resource. I setup the resource
as a material resource and assigned it to my project plan. When I check the
view assignments function of my material source in resource center, the start
and finish dates are empty and there is no gantt chart, all I see here is the
project that the resource is assigned to. Is it the correct way to handle
this type of resource?
I would want to show the list of project, task, planned start and end date
for this resource in a view, is there any other way to achieve that?
Regards
Godrid