C
CQ
I am Using Project Server 2007 and in Project Professional I am manually
entering a cost int othe "Actual Cost" field. I have gone to Tools, Option,
Calculation and unchecked the box for letting project calculate costs since i
am not using any other costing method inside of Project. I enter amounts
into the Cost field manually. All is well and the system works fine. When I
know what a task actually cost me, I come back and enter that into "Actual
Cost" field.
The issue is that when I enter the "Actual Cost" it automatically adjusts
the "Cost" field to match the Actual Cost field. I don't want it to do that.
I can immediately go back and change "Cost" back to the original amount but
that is time consuming and sort of ruins the purpose of having entered the
cost in the first place. How and where is a setting that makes the "Cost"
field NOT modify itself to match "Actual Cost"?
entering a cost int othe "Actual Cost" field. I have gone to Tools, Option,
Calculation and unchecked the box for letting project calculate costs since i
am not using any other costing method inside of Project. I enter amounts
into the Cost field manually. All is well and the system works fine. When I
know what a task actually cost me, I come back and enter that into "Actual
Cost" field.
The issue is that when I enter the "Actual Cost" it automatically adjusts
the "Cost" field to match the Actual Cost field. I don't want it to do that.
I can immediately go back and change "Cost" back to the original amount but
that is time consuming and sort of ruins the purpose of having entered the
cost in the first place. How and where is a setting that makes the "Cost"
field NOT modify itself to match "Actual Cost"?