I am using Project Server 2007, tasks with Fixed Work, Resources update by
percentage complete, all resources on standard (8-5, 8 hour day) calendar.
Usually, when the resource updates a task, all works as expected. However,
when they update a task AND change the Finish Date of the task the system
automatically is modifying their units (from 100%) and the duration of the
task. So, I am having things like a one day duration task with 8 hours of
work suddenly jump to 5 days of duration and changing the units to something
like 20%, the work is staying at 8 hours. I expected that the task would
split to the new finish date, the duration would increase but the units
wouldn't change. How do I keep the units from changing?
percentage complete, all resources on standard (8-5, 8 hour day) calendar.
Usually, when the resource updates a task, all works as expected. However,
when they update a task AND change the Finish Date of the task the system
automatically is modifying their units (from 100%) and the duration of the
task. So, I am having things like a one day duration task with 8 hours of
work suddenly jump to 5 days of duration and changing the units to something
like 20%, the work is staying at 8 hours. I expected that the task would
split to the new finish date, the duration would increase but the units
wouldn't change. How do I keep the units from changing?