E
Ertan Sekmen
I'm studying on a different approach to a project. Is it possible to fix the
task budget, and enter resource cost per hour lets say, then calculate task
duration automatically?
for an example I have 100$ for a task to complete. and I pay 20$ per hour to
a worker. I want 5 hours as a task duration to be displayed on gannt chart.
In this project it is not necesseray that task is completed or not. What is
important that I have to finish the budget and calculate maximum work time.
any help is appriciated.
thanks in advance.
ertan
task budget, and enter resource cost per hour lets say, then calculate task
duration automatically?
for an example I have 100$ for a task to complete. and I pay 20$ per hour to
a worker. I want 5 hours as a task duration to be displayed on gannt chart.
In this project it is not necesseray that task is completed or not. What is
important that I have to finish the budget and calculate maximum work time.
any help is appriciated.
thanks in advance.
ertan