B
Björn Wächter
Hello,
I have a resource working over a longer time period on the same
task with 20% of its time. In parallel the resource should work
on other tasks using the 80% rest time. My problem is that ms
project is scheduling the other tasks behind the 20% task when I
use auto leveling. It looks like it is not possible to use the
80% rest of the resource. After auto leveling it looks like this:
|-----------------| mike[20%]
|------| mike
I would expect this result
|-----------------| mike[20%]
|--------| mike
The task takes a bit longer but is executed in parallel.
Is there an option how i can do this in ms project?
Thanks,
Björn
I have a resource working over a longer time period on the same
task with 20% of its time. In parallel the resource should work
on other tasks using the 80% rest time. My problem is that ms
project is scheduling the other tasks behind the 20% task when I
use auto leveling. It looks like it is not possible to use the
80% rest of the resource. After auto leveling it looks like this:
|-----------------| mike[20%]
|------| mike
I would expect this result
|-----------------| mike[20%]
|--------| mike
The task takes a bit longer but is executed in parallel.
Is there an option how i can do this in ms project?
Thanks,
Björn