Ã
Ã…sa Larsson
We have two resources working together on one task (totally 16 h). Resource 1
is available 100% for the project and resource 2 is only available 20%. These
two resources needs to do the task (reviews) simulatiously, when resource 2
is available. The work load for this task is the same for both resources (16
h each).
We have tried Fixed Duration, Fixed Unit and Fixed Work but with no success.
In the tests we've done;
* the total work has changed for a task
* work per resource has changed or
* the task is not performed on the same date (which is a must).
Any ideas of how to set-up this correctly, to avoid manual work arounds?
Thanks in advance.
Ã…sa.
is available 100% for the project and resource 2 is only available 20%. These
two resources needs to do the task (reviews) simulatiously, when resource 2
is available. The work load for this task is the same for both resources (16
h each).
We have tried Fixed Duration, Fixed Unit and Fixed Work but with no success.
In the tests we've done;
* the total work has changed for a task
* work per resource has changed or
* the task is not performed on the same date (which is a must).
Any ideas of how to set-up this correctly, to avoid manual work arounds?
Thanks in advance.
Ã…sa.