N
Newbie
I am new to MS Project. I am using Project 2003.
Many of my resources are part-time available only 50% (or less) of the time.
I want to use *actual duration* to let the resources know the actual time a
task should take: e.g., 20 hours although that 20 hours will be spread over a
standard 40 hour week. The duration is also important for me in calculating
the actual cost - the same 20 hours * $$.
I did change the calendar for a resource, as discussed previously in the
forum. However, I didn't see any changes to the way things appeared. (In the
Base Calendar portion of my resource sheet Standard is listed. The pull down
lists 24-hours, Night shift and standard. So I have not idea if the changes I
made are being implemented.)
I have the MS Project 2003 Bible and have read it all day... - to no avail
on this issue.
Please help - this is a new job...
Many of my resources are part-time available only 50% (or less) of the time.
I want to use *actual duration* to let the resources know the actual time a
task should take: e.g., 20 hours although that 20 hours will be spread over a
standard 40 hour week. The duration is also important for me in calculating
the actual cost - the same 20 hours * $$.
I did change the calendar for a resource, as discussed previously in the
forum. However, I didn't see any changes to the way things appeared. (In the
Base Calendar portion of my resource sheet Standard is listed. The pull down
lists 24-hours, Night shift and standard. So I have not idea if the changes I
made are being implemented.)
I have the MS Project 2003 Bible and have read it all day... - to no avail
on this issue.
Please help - this is a new job...