Hello Everyone,
I have a requirement where a resource is allocated on three different
projects say 30 % on Project A , 50% on Project B and 20% on Project C.
Is there a way to define the resource commitment (partial allocation)
to a project at the project level (A,B,C) so that PM does not have to
go back every time project is opened in Microsoft Project and edit the
resource availability to partial allocation to certain percentage since
Microsoft Project resets it back to 100% after you close the project.
Any input on this will be highly appreciated?
Thanks in advance.
-Raj
I have a requirement where a resource is allocated on three different
projects say 30 % on Project A , 50% on Project B and 20% on Project C.
Is there a way to define the resource commitment (partial allocation)
to a project at the project level (A,B,C) so that PM does not have to
go back every time project is opened in Microsoft Project and edit the
resource availability to partial allocation to certain percentage since
Microsoft Project resets it back to 100% after you close the project.
Any input on this will be highly appreciated?
Thanks in advance.
-Raj