C
careta
Hi All
I want to link a task in one project to another project. I do this by "Copy" of the source task and "Paste special" in the target project. This works fine as long as the source task has no predecessors in its own project. If it has predecessors, the target project references them as tasks of its own, messing all the timing info.
In an example, let's say that task 30 has task 15 as his predecessor. When I copy & paste special task 30 to target project (being now task 40, for ex.), target project makes this new task dependant of his own task 15 (if it doesn't exist, it links it to project start date)
Is there any way to avoid this annoying behaviour
Thanks
careta
I want to link a task in one project to another project. I do this by "Copy" of the source task and "Paste special" in the target project. This works fine as long as the source task has no predecessors in its own project. If it has predecessors, the target project references them as tasks of its own, messing all the timing info.
In an example, let's say that task 30 has task 15 as his predecessor. When I copy & paste special task 30 to target project (being now task 40, for ex.), target project makes this new task dependant of his own task 15 (if it doesn't exist, it links it to project start date)
Is there any way to avoid this annoying behaviour
Thanks
careta