Path to create different calendar

K

ks2008

I understand the meaning of each calendar listed below.
Could someone provide me the path to create same ?
Base calendar
Project calendar
Resource calendar
Task calendar .

Thanks
KS
 
R

reza

KS 2008---

If you want to create new calendar, Tools---Change Working Time--- Create
New Calendar.
- Project Calendar, Apply this new calendar in Project--Project
Information--Calendar
- Resource Calendar, Apply this new calendar in Resource Sheet then choose
new calendar in Base Calendar Coloum
- Task Calendar, Apply this calendar in Task Information---Advance
Tab--Calendar

hope this help...

reza
 
A

Akram Najjar

Hi KS

Like Trevor said: all new Calendars can be created under TOOLS / CHANGE
WORKING TIME. This post defines where to use them (sorry if you already know
that).

After you create Calendars for each of these: Project, Task(s), Resource(s)
then you need to assign these calendars to their respective parents. (This
may be a repetition but . . .)

1) Project Calendar is set in the PROJECT/PROJECT INFORMATION form
I presume this would be called the Base Calendar. Maybe a Base Calendar is a
calendar that you use to copy to create others. Functionally, there is no
Base Calendar as far as I Know.

2) Don't forget a hidden risk: right click the time part of the Gantt view
and go to Non-Working Time. Assign the Project Calendar to that otherwise you
won't see the days off that you set.

3) Task: after you create a Task, double click it to get the Task Info box.
On the Advanced Tab you can assign the Calendar of your choice.

4) Resources: on the Resource Sheet itself, there is a column to assign a
calendar to a Resource Sheet. Note that having created a Resource, you can
double click it and get to the Res Info box. There, you can adjust the
specific days of availability for that Resource. For example, 4 different
Resources use the MORNING SHIFT calendar. But Res1 has a holiday from 1 to 30
Sep. Here is where you can specify that.

Hope that fit the purpose!
Akram
 
M

Michael.Tarnowski

KS 2008---

If you want to create new calendar, Tools---Change Working Time--- Create
New Calendar.
- Project Calendar, Apply this new calendar in Project--Project
Information--Calendar
- Resource Calendar, Apply this new calendar in Resource Sheet then choose
new calendar in Base Calendar Coloum
- Task Calendar, Apply this calendar in Task Information---Advance
Tab--Calendar

hope this help...

reza

HI everybody involved in this thread,

I assume all of us know how to define the mentioned calendar types in
MSP - ks2008's question is maybe more a kind of short guideline: WHEN
(in which planning situation) and WHY (with which consequence) each
calendar type is approriate.
Cheers Michael
 