M
Mike
Hi,
i have a problem with setting a new value for 'RemainingWork' for
assignments with tracking mode 1.
The problem is, that if i set only 'RemainingWork' the value for
'PercentWorkComplete' in the assignment is always set to 100%.
Following the PDS Reference, for this tracking mode, it should also be
possible to set the value for 'ActualWork'. But then i get error 122
(Actuals are reported in a method other than the locked-down reporting
method).
Does someone know, how to change 'RemainingWork' for assignments with
tracking mode 1?
Many thanks in advance,
Mike
i have a problem with setting a new value for 'RemainingWork' for
assignments with tracking mode 1.
The problem is, that if i set only 'RemainingWork' the value for
'PercentWorkComplete' in the assignment is always set to 100%.
Following the PDS Reference, for this tracking mode, it should also be
possible to set the value for 'ActualWork'. But then i get error 122
(Actuals are reported in a method other than the locked-down reporting
method).
Does someone know, how to change 'RemainingWork' for assignments with
tracking mode 1?
Many thanks in advance,
Mike