PDS % Complete Calculation

I

Iain Carlin

Hi,

I have written a timesheet application that uses AssignmentsSave to update
the Actual and Remaining work on a project. PWA is set to track progress
using the "Actual Work Done and Work Remaining" method.

According to the PDS documentation, setting the Remaining work to 0 should
set the task to be 100% complete - which it does except when the Actual Work
on the task is 0.

In this case the %Complete is always set to 0. I've read a few posts that
suggest various patches, however I have now installed Project/Project Server
SP2 and the problem remains.

The issue seems to be with PDS, as when I look in the MSP_WEB_ASSIGNMENTS
table it sets %Complete there to be 0 (I've manually set it to some other
value and PDS always overwrites it). This does not get corrected when the
Project Manager runs Update Project Progress.

Anybody struck this problem before?

Iain Carlin
 