Hallo,
i need to update Resource enterprise values and I have send to PDS service
this XML request. I have my resource Checked out and the reply is an
database error. What i make inncorrect. When i need to update EROC what does
meen the ValueUID is the same nuber as UID of the field or is the value in
RBS.
thanks
<Request>
<ResourceCodeValuesUpdate>
<ResourceUID>000</ResourceUID>
<!--Correct UID -->
<ResourceName>name surname</ResourceName>
<!--Correct Name -->
<AutoCheckin>1</AutoCheckin>
<Columns>
<Column>
<UID>205521542</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521543</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521544</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521545</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521546</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521547</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521548</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521549</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521550</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521536</UID>
<Value>some text</Value>
<!--Custom Field -->
<ValueUID>205521536</ValueUID>
<!--EROC -->
</Column>
<Column>
<UID>205521540</UID>
<Value>some text</Value>
<!--Custom Field -->
<ValueUID>205521540</ValueUID>
<!--EROC -->
</Column>
</Columns>
</ResourceCodeValuesUpdate>
</Request>
<!--
205521542 Resource Enterprise Text1
205521543 Resource Enterprise Text2
205521544 Resource Enterprise Text3
205521545 Resource Enterprise Text4
205521546 Resource Enterprise Text5
205521547 Resource Enterprise Text6
205521548 Resource Enterprise Text7
205521549 Resource Enterprise Text8
205521550 Resource Enterprise Text9
205521536 Resource Enterprise Resource Outline Code28
205521540 RBS (Resource Enterprise Resource Outline Code30 is the resource
breakdown structure)
-->
i need to update Resource enterprise values and I have send to PDS service
this XML request. I have my resource Checked out and the reply is an
database error. What i make inncorrect. When i need to update EROC what does
meen the ValueUID is the same nuber as UID of the field or is the value in
RBS.
thanks
<Request>
<ResourceCodeValuesUpdate>
<ResourceUID>000</ResourceUID>
<!--Correct UID -->
<ResourceName>name surname</ResourceName>
<!--Correct Name -->
<AutoCheckin>1</AutoCheckin>
<Columns>
<Column>
<UID>205521542</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521543</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521544</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521545</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521546</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521547</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521548</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521549</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521550</UID>
<Value>some text</Value>
<!--Custom Field -->
</Column>
<Column>
<UID>205521536</UID>
<Value>some text</Value>
<!--Custom Field -->
<ValueUID>205521536</ValueUID>
<!--EROC -->
</Column>
<Column>
<UID>205521540</UID>
<Value>some text</Value>
<!--Custom Field -->
<ValueUID>205521540</ValueUID>
<!--EROC -->
</Column>
</Columns>
</ResourceCodeValuesUpdate>
</Request>
<!--
205521542 Resource Enterprise Text1
205521543 Resource Enterprise Text2
205521544 Resource Enterprise Text3
205521545 Resource Enterprise Text4
205521546 Resource Enterprise Text5
205521547 Resource Enterprise Text6
205521548 Resource Enterprise Text7
205521549 Resource Enterprise Text8
205521550 Resource Enterprise Text9
205521536 Resource Enterprise Resource Outline Code28
205521540 RBS (Resource Enterprise Resource Outline Code30 is the resource
breakdown structure)
-->