In MS Project Client, you can click:
Report->See how Resource´s time is allocated

Are there any PDS Resource Methods (or other methods) that give you info of
how many tasks each Resource has, how many Work hours etc.?

Many thanks,
Gunnar
 
E

Ed Morrison

Gunnar,
As you probably know by now, the PDS is very limited in the information that
it can return. As far as I know, the PDS Reference is a complete listing of
the methods available.

You may have to either create a PDS extension or query SQL directly for the
info you need. You can find it in the msp_assignments table.
 
G

G u n n a r

What about the AssignmentsGet Method?

Thanks a lot mr.Morrison,
Gunnar

------------------------------------------------------------------------
 