pending approval tasks for the PM has left.

A

Ahmed Ghaith

Dear All,

I use project server 2007
Are they having any way to approve the pending tasks for the project manger
had left the organization?
Because some resources modify the old tasks and when I check in the pending
approval list I sow the status manger for this task is left before.
I know the resources should be create a new tasks not modify the old one,
but that’s a scenario.
I need a way to approve the pending tasks on the old PM,

Sorry for lengthening.
Regards,
 
B

Ben Howard

Short of editing the database, your only way is to log in as the PM and do
the approval as that user.
 
A

Ahmed Ghaith

Hi,
But how editing DB are you have a query for this purpose.

Thanks for response.
--------------
 
A

Ahmed Ghaith

Hi,
But how editing DB are you have a query for this purpose.

Thanks for response.
--------------
 
B

Ben Howard

Alas I don't, but I expect you'll have to relace the resource GUID of the old
PM (actually status manager) with the resource GUID of the new Status Manager
for the outstanding approvals.
--
Thanks, Ben.

Please rate this post if it helped.
http://appleparkltd.spaces.live.com/
 
B

BoggyBoy

You may want to try this - cant promise it will work..

Open the project plans as an admin with MS Project
Insert the Status Owner field
Change the Status Owner to another person
Republish the plan
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top