A
avimia
Hi experts,
Hope you all are doing well. First, let me start out by saying thank you to
all you experts who have answered my posts in the past. It's been great
having people help (without biting my head off). PMs are just the best ;-)
My question today is probably very silly to most of you. But, it's about
tracking... or just generally showing... when someone assigned on a project
is sick or out of work. For example, I have a Project A and Tammy is one of
the resources. Tammy happens to be one of the only people who can do her
specific tasks of this Project A. The timeline of Project A is going along
fine. However... obviously my time line is not following the plan due to
Tammy having been off sick for 2 days.
Now, I understand that I could probably go in and adjust my finish-dates for
her task. However, (and since I allowed for a little "fudge time") I don't
want to change ANY timelines (her task or the over all project) as I can
still see her being able to finish by her due original due date. By keeping
her on track like this, my project is still due to come in a bit under
schedule. So, that's fine too. But.. my question is.... where do I enter a
note or two about her having been off sick for 2 days (after all, if we do
come in under schedule.. it will look even better that the team so well even
after Tammy's absense).
I know I can add something in the "notes", or even in an added text field at
the end. But, I'm looking to find out how other PMs deal with this? (I really
just hate the "Notes" because they're just NOT convenient to see at a QUICK
glance).
Thanks for your input,
avimia
Hope you all are doing well. First, let me start out by saying thank you to
all you experts who have answered my posts in the past. It's been great
having people help (without biting my head off). PMs are just the best ;-)
My question today is probably very silly to most of you. But, it's about
tracking... or just generally showing... when someone assigned on a project
is sick or out of work. For example, I have a Project A and Tammy is one of
the resources. Tammy happens to be one of the only people who can do her
specific tasks of this Project A. The timeline of Project A is going along
fine. However... obviously my time line is not following the plan due to
Tammy having been off sick for 2 days.
Now, I understand that I could probably go in and adjust my finish-dates for
her task. However, (and since I allowed for a little "fudge time") I don't
want to change ANY timelines (her task or the over all project) as I can
still see her being able to finish by her due original due date. By keeping
her on track like this, my project is still due to come in a bit under
schedule. So, that's fine too. But.. my question is.... where do I enter a
note or two about her having been off sick for 2 days (after all, if we do
come in under schedule.. it will look even better that the team so well even
after Tammy's absense).
I know I can add something in the "notes", or even in an added text field at
the end. But, I'm looking to find out how other PMs deal with this? (I really
just hate the "Notes" because they're just NOT convenient to see at a QUICK
glance).
Thanks for your input,
avimia