M
ma.u
Hi.
I have a Project db on an Oracle, and I have a procedure that update
TASK_PCT_COMP field (percent complete) and other fields in MSP_TASKS.
Somtimes it work correctly, but sometimes, when Project loads an
updated project, the percentage appers to be divided by duration of
the task (in days).
Why does it appen?
Thanks.
I have a Project db on an Oracle, and I have a procedure that update
TASK_PCT_COMP field (percent complete) and other fields in MSP_TASKS.
Somtimes it work correctly, but sometimes, when Project loads an
updated project, the percentage appers to be divided by duration of
the task (in days).
Why does it appen?
Thanks.