Has anyone had this problem?

I have a project with tasks assigned to a resource. The current
percent complete is 100% on several tasks. The tasks are assigned to
a single resource.

When the resource goes to project web access, the tasks show 50%
complete. I have checked in the database, and the tasks are 100%
complete. I have re-published the project, waited a while, and they
still show 50%, but only in the tasks screen.

Is there something I am missing?

Thanks,
Jeff
 
D

Dale Howard [MVP]

Jeff --

When you republish the project, did you complete the following steps:

1. Click Collaborate - Publish - Republish Assignments
2. Select the "Overwrite actual work entered by resources" option
3. Click OK

Doing so will "push" the % complete from the project plan to the user's
timesheet in PWA. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
J

Jason M

Dale,
Would your steps to synchronize still work if you selected Collaborate -
Publish -All Information?
 
D

Dale Howard [MVP]

Jason M --

No. That is why I specified the exact steps you must perform to "push" the
% Work Complete from the Microsoft Project plan to the PWA timesheet of the
resource assigned to the task. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the books on Project Server"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top