Percent complete isn't being updated in the task level from subtasks

O

OnamikaConsulting

I don't know if this is a bug in the project or not, After I put 100%
complete in the subtasks, the task percent completed still stays at 0%
which is very strange.
 
J

John

I don't know if this is a bug in the project or not, After I put 100%
complete in the subtasks, the task percent completed still stays at 0%
which is very strange.

onamikaconsulting,
No need to post a new message.

What version of Project are you using? Does this occur on multiple
summary lines or just some? Does this occur on more than one Project
file? Are you sure you are talking about he % Complete field and not
some other field? Does this occur in a single project file or is it part
of a consolidated master?

More information would help.
John
Project MVP
 
D

Dave

I don't know if this is a bug in the project or not, After I put 100%
complete in the subtasks, the task percent completed still stays at 0%
which is very strange.

Try promoting the tasks so that they are at the same level as the
summary task, deleting that, entering a new one and demoting the tasks
under the new task.

Dave
 