M
Master Chief
Quick Question,
We've found 2 issue with Percent Complete in MSPP2003.
The first issue is addressed by the HOTFIX mentioned in
KB Article 891648. We refer to this as the 100% to 0% issue.
The second percent complete issue, not addressed by KB Article 891648, is
when the PM attempts to set the task to 100% complete it returns to 99%
complete.
In all situations we review the Resource Usage screen to ensure the
resources assignment remaining work is 0h. If it has remaining hours we
adjust the remaining hours on the resources timesheet and resubmit and accept
the update.
This normally resolves this issue. However, occasionally, the Resources
Usage reamining work and Task Sheet remaining work are equal, 0h, but the
task will not set to 100% complete. It continually returns to 99% complete.
Any help you can provided is greatly appreciated.
We've found 2 issue with Percent Complete in MSPP2003.
The first issue is addressed by the HOTFIX mentioned in
KB Article 891648. We refer to this as the 100% to 0% issue.
The second percent complete issue, not addressed by KB Article 891648, is
when the PM attempts to set the task to 100% complete it returns to 99%
complete.
In all situations we review the Resource Usage screen to ensure the
resources assignment remaining work is 0h. If it has remaining hours we
adjust the remaining hours on the resources timesheet and resubmit and accept
the update.
This normally resolves this issue. However, occasionally, the Resources
Usage reamining work and Task Sheet remaining work are equal, 0h, but the
task will not set to 100% complete. It continually returns to 99% complete.
Any help you can provided is greatly appreciated.