Percent completed doesn't get updated in the task level after changing in the subtasks

O

OnamikaConsulting

If I put 100% in the subtask level for percent completed, task still
stays at 0%, may be a Microsoft bug!
 
J

John

If I put 100% in the subtask level for percent completed, task still
stays at 0%, may be a Microsoft bug!

onamikaconsulting,
The most common reason for this apparent "bug" is that calculation is
set for manual. Go to Tools/Options/Calculation tab and make sure
calculation is set for automatic.

John
Project MVP
 
O

OnamikaConsulting

onamikaconsulting,
The most common reason for this apparent "bug" is that calculation is
set for manual. Go to Tools/Options/Calculation tab and make sure
calculation is set for automatic.

John
Project MVP

No, I checked and it's set to automatic - any other reason it stays at
0%?
 
O

OnamikaConsulting

onamikaconsulting,
The most common reason for this apparent "bug" is that calculation is
set for manual. Go to Tools/Options/Calculation tab and make sure
calculation is set for automatic.

John
Project MVP

Calculation was already set to Automatic. Any other reason why it acts
this way?
 