A
Andrew Black
I have setup a project with about 100 tasks and subtasks. In most
cases, no task necessarily has to preceed another one. I would like
Project to automatically calculate start and end dates based on the
duration of each task and the resources assigned to it.
For example, I have a certain groups of tasks which will each take one
day. I've assigned one resource to it and setup his schedule in the
resource manager. Yet Project is assuming that that one resource can
do 20 1 day tasks in one day.
One solution is to make each task have a predecessor of the previous
task (so 1 is a predecessor of 2, etc.), but this takes a long time to
enter. Further, if I assign another resource to the group of tasks, it
won't calculate start and end time accurately anymore.
Is there some way I can configure Project so that it realizes there's
just one resource for a group of tasks and have it calculate the total
duration as the sum of each task duration?
Any help would be greatly appreciated!
cases, no task necessarily has to preceed another one. I would like
Project to automatically calculate start and end dates based on the
duration of each task and the resources assigned to it.
For example, I have a certain groups of tasks which will each take one
day. I've assigned one resource to it and setup his schedule in the
resource manager. Yet Project is assuming that that one resource can
do 20 1 day tasks in one day.
One solution is to make each task have a predecessor of the previous
task (so 1 is a predecessor of 2, etc.), but this takes a long time to
enter. Further, if I assign another resource to the group of tasks, it
won't calculate start and end time accurately anymore.
Is there some way I can configure Project so that it realizes there's
just one resource for a group of tasks and have it calculate the total
duration as the sum of each task duration?
Any help would be greatly appreciated!