L
luai7
Hi,
We are using Microsoft Project Server 2007 & Microsoft Office Project 2007.
Currently, I am in the process of building proof of concept tests so as to
adopt this product in our enterprise.
I created 4 users and mapped them to their corresponding windows domain
users. Those 4 users were added as "Team Members" in Project server.
I added my self as a "Team Leader" & "Resource Manager". The idea here is
that I want to simulate the task assignment, reporting, then acceptance or
rejection.
Now when I open a plan that contains assignments to these resources I
receive a message at startup: "You do not have permissions to see the data
for all the enterprise resources in this project" and then a list of resource
names appear incuding all defined resources!!
What should I do??
We are using Microsoft Project Server 2007 & Microsoft Office Project 2007.
Currently, I am in the process of building proof of concept tests so as to
adopt this product in our enterprise.
I created 4 users and mapped them to their corresponding windows domain
users. Those 4 users were added as "Team Members" in Project server.
I added my self as a "Team Leader" & "Resource Manager". The idea here is
that I want to simulate the task assignment, reporting, then acceptance or
rejection.
Now when I open a plan that contains assignments to these resources I
receive a message at startup: "You do not have permissions to see the data
for all the enterprise resources in this project" and then a list of resource
names appear incuding all defined resources!!
What should I do??