Hi,
We have problems with Project Managers being able to "Build Team on
Project". I've seen various posts and the examples on MSDN and everything
seems to be right (I think).
The problem appears to be the calculation of effective rights. Using the
effective rights tool I'm being told that the user has an effective "deny"
permission however looking at the detail I don't see why.
The detail in effective rights tool says permission "Allow" as member of the
"Project Managers" group and no permission as part of the "Team Members"
group. Which as I understand it should result in effective permission "Allow"
for the user, but according to the tool it's effective permission "Deny".
Am I mis-understanding or is there something else I should be looking at?
We are running Project Server 2007.
Cheers,
Cameron.
We have problems with Project Managers being able to "Build Team on
Project". I've seen various posts and the examples on MSDN and everything
seems to be right (I think).
The problem appears to be the calculation of effective rights. Using the
effective rights tool I'm being told that the user has an effective "deny"
permission however looking at the detail I don't see why.
The detail in effective rights tool says permission "Allow" as member of the
"Project Managers" group and no permission as part of the "Team Members"
group. Which as I understand it should result in effective permission "Allow"
for the user, but according to the tool it's effective permission "Deny".
Am I mis-understanding or is there something else I should be looking at?
We are running Project Server 2007.
Cheers,
Cameron.