D
Dytham
A Project 2003 user has spent a lot of their time in creating a new calendar
containing public and corporate holidays for many years ahead. Lets say it is
called "Corporate".
Using Project Information dialogue, calendar Corporate has been named as
base calendar for the project.
Problem: When a new resource is added, their Base Calendar is still being
set to default of Standard.
Attempted work-arounds of getting rid of Standard to then rename Corporate
are prohibited.
I can see no solution other than to re-do the work in tailoring Standard.
Can anyone else ?
Calendar Standard seems to be sacrosanct !
containing public and corporate holidays for many years ahead. Lets say it is
called "Corporate".
Using Project Information dialogue, calendar Corporate has been named as
base calendar for the project.
Problem: When a new resource is added, their Base Calendar is still being
set to default of Standard.
Attempted work-arounds of getting rid of Standard to then rename Corporate
are prohibited.
I can see no solution other than to re-do the work in tailoring Standard.
Can anyone else ?
Calendar Standard seems to be sacrosanct !