J
Jamie Bumsted
Hi -
Perhaps I am going about this the wrong way, but I would like to utilize
dates with a 95% confidence interval. In order to do this I think I need to
add 2 standard deviations to the finish date after performing the PERT
estimate. I have been able to create a custom column with this duration for
each task, but I can't seem to figure out how to have Project use this
duration to determine the projected start and finish dates. Is there a way
to do this automatically?
Thanks in advance.
Jamie
Perhaps I am going about this the wrong way, but I would like to utilize
dates with a 95% confidence interval. In order to do this I think I need to
add 2 standard deviations to the finish date after performing the PERT
estimate. I have been able to create a custom column with this duration for
each task, but I can't seem to figure out how to have Project use this
duration to determine the projected start and finish dates. Is there a way
to do this automatically?
Thanks in advance.
Jamie