Hi,

After running the calculate tool in the PERT Analysis toolbar I need to
change some durations manually.

How can I run a new calculation without changing the task duration of those
tasks that I changed manually?

Thanks in advance
 
M

Mike Glen

Hi PDP,

Welcome to this Microsoft Project newsgroup :)

If you want to keep the Duration you've changed, then make the pessimistic,
expected and optimistic the same.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen