Hi ageped,
Welcome to this Microsoft Project newsgroup
This isn't directly possible within Project because of the way Project
calculates costs. For a PERT analysis you input three times - worst
estimate, best estimate and most likely estimate of the duration. Project
will then take the resource cost figure, multiply it by each of the three
durations and thus give 3 cost values. There is no way you can enter 3
resource cost figures to be taken into account, unless you create 3 versions
of the same project. You would then have to consider 3 entries of fixed
costs which only have one field. Not feasible - sorry.
FAQs, companion products and other useful Project information can be seen at
this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
ageped said:
I would like to perform a PERT-analysis on costs, not duration. Anyone
know how?