PERT Duration Issues

V

vandermt

Hello,
We are using Project Professional 2003 (11.2.2005.1801.15) SP2 and Project
Web Access.

We are using the PERT calculation feature of MS Project. I enter a task with
Opt Dur=1 mon, Exp. Dur = 6 mon and Pess Dur= 16 Mons. Pressong the CACULATE
PERT icon creates a Duration = 0.01 mons?

Also when we add a new task we get a scheduling message statis the task
cannot be completed in the time allocated because of a scheduling conflict.
We even get this for new projects.

These errors started to appear yesterday for the first time.

Has anyone seen anything like this?

Help.
 
J

Jack Dahlgren

Resolve the scheduling conflict first. It is very likely that it is why you
are getting strange results from PERT.
If you are getting a scheduling message when you insert a single task in a
new blank project, then I suspect something is wrong with your project
installation. Try repairing or reinstalling (from the "Add or Remove
Programs" control panel.
-Jack
 
V

vandermt

Just an update. After much digging we found a EntrpiseDuration Field
Corrupted. After deleting the field from the global template all apears to
work again.
 