V
vandermt
Hello,
We are using Project Professional 2003 (11.2.2005.1801.15) SP2 and Project
Web Access.
We are using the PERT calculation feature of MS Project. I enter a task with
Opt Dur=1 mon, Exp. Dur = 6 mon and Pess Dur= 16 Mons. Pressong the CACULATE
PERT icon creates a Duration = 0.01 mons?
Also when we add a new task we get a scheduling message statis the task
cannot be completed in the time allocated because of a scheduling conflict.
We even get this for new projects.
These errors started to appear yesterday for the first time.
Has anyone seen anything like this?
Help.
We are using Project Professional 2003 (11.2.2005.1801.15) SP2 and Project
Web Access.
We are using the PERT calculation feature of MS Project. I enter a task with
Opt Dur=1 mon, Exp. Dur = 6 mon and Pess Dur= 16 Mons. Pressong the CACULATE
PERT icon creates a Duration = 0.01 mons?
Also when we add a new task we get a scheduling message statis the task
cannot be completed in the time allocated because of a scheduling conflict.
We even get this for new projects.
These errors started to appear yesterday for the first time.
Has anyone seen anything like this?
Help.