D
DanG
When using the PERT Entry Toolbar, the "Gantt" charts on the right side of
the screen show the correct durations for each of the tasks for the
Optimistic, Expected, and Pessimistic views. They also show the
(Finish-to-Start) predecessor relationship of the tasks.
However, it doesn't show the Optimistic, Expected, or Pessimistic schedules
- all the tasks in each view start at the project start date and last for
whatever their duration is. Why is that, and can I change it?
Thanks,
Dan
the screen show the correct durations for each of the tasks for the
Optimistic, Expected, and Pessimistic views. They also show the
(Finish-to-Start) predecessor relationship of the tasks.
However, it doesn't show the Optimistic, Expected, or Pessimistic schedules
- all the tasks in each view start at the project start date and last for
whatever their duration is. Why is that, and can I change it?
Thanks,
Dan