R
Ryan Rupert
KEYWORDS
*Master project
*Portfolio
*Programs
*Linked Projects
*Inserted Project
*Consolidated Project
EXPLANATION
-I am just now broaching this subject for our solution,
for every project we perform phases (Discovery, Analysis,
Design, Implementation)
-in effect these are 4 seperate projects that may or may
not make it to the last phase Implementation, we could
have a client approve the Discovery phase but then not
approve Analysis so we would stop there
-we will go from a Proposal process (using Project 2007
on MOSS 2007), to the first phase Discovery which will be
in effect the "master project", budgeting, resources, reports,
documents will all be independant of any subsequent phase
but of course would be "logically" associated if another
project phase were to be approved by a client
-I like the idea of creating a project template that will include
all of these phases, but I would only create a Project Workspace
for a given phase if that phase is approved by my client, so a
Master Project plan could have generic tasks for future phases
but would just not have any resources or time allocated until
inception
-so, I am envisioning a Project Workspace and Project "master"
that starts with my phase "Discovery" and in the end, potentially
has sub-workspaces/sub-projects for each of the subsequent
phases
-now, each subseqent phase would have activity that is
interrelated and in most cases dependant (predecessors, etc)
with the previous phase so I want them to remain logically
associated, I am thinking Master Project and sub-projects is
the way to do this
QUESTION
-is my explanation above enough info to point me in the right direction
*Master project
*Portfolio
*Programs
*Linked Projects
*Inserted Project
*Consolidated Project
EXPLANATION
-I am just now broaching this subject for our solution,
for every project we perform phases (Discovery, Analysis,
Design, Implementation)
-in effect these are 4 seperate projects that may or may
not make it to the last phase Implementation, we could
have a client approve the Discovery phase but then not
approve Analysis so we would stop there
-we will go from a Proposal process (using Project 2007
on MOSS 2007), to the first phase Discovery which will be
in effect the "master project", budgeting, resources, reports,
documents will all be independant of any subsequent phase
but of course would be "logically" associated if another
project phase were to be approved by a client
-I like the idea of creating a project template that will include
all of these phases, but I would only create a Project Workspace
for a given phase if that phase is approved by my client, so a
Master Project plan could have generic tasks for future phases
but would just not have any resources or time allocated until
inception
-so, I am envisioning a Project Workspace and Project "master"
that starts with my phase "Discovery" and in the end, potentially
has sub-workspaces/sub-projects for each of the subsequent
phases
-now, each subseqent phase would have activity that is
interrelated and in most cases dependant (predecessors, etc)
with the previous phase so I want them to remain logically
associated, I am thinking Master Project and sub-projects is
the way to do this
QUESTION
-is my explanation above enough info to point me in the right direction