There is no "phase" column in any of the task tables or the available fields
in the task database itself in Project so I don't have a clue what you're
referring to. Did someone else set up that plan for you or send it to you,
or perhaps customize the Project tables in your installation? If so, you'll
need to ask them the function of that column since I'm positive it is a
user-defined field rather than standard equipment from MS. In any case,
representing project phases is one of the common uses of high-level summary
tasks and all one need do to create them is to insert the name at the
approriate place in the plan and indent all the other tasks (which can be
either performance tasks or smaller summaries which themselves contain finer
detail task breakdowns) that are subordinate to them.
<example>
Phase 1
Work 1.1
Summary 1.2
Work 1.2.1
Work 1.2.2
Work 1.2.3
Work 1.3
Work 1.4
Phase 2
<etc>
Steve House [MVP]
M.S Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs