K
Kris R.
I'm confused about the Physical % complete field. The help says it is a
manually entered field, but for summary tasks, you cannot edit it, NOR does
it roll up. It's just alwasy 0% for a summary task.
For example:
NAME Phys % comp
===================================
RES02DEF 0%
--230kV oil 50%
--Proj mgmt 100%
--cable design 100%
--System Plan 100%
--Project Plan 25%
RES02DEF is the summary task, but I cannot edit the Physical % complete
field (like I can for its children), AND it's set to 0%, no matter what the
values of its children.
(1) Why can't I change it?
(2) And if it can't be changed, why doesn't it do something useful, like
roll up??
(Or is there something special I should do to make it roll up? I've tried
hitting the "calculate now" button, but it doesn't make a difference.)
Thanks,
Kris R.
manually entered field, but for summary tasks, you cannot edit it, NOR does
it roll up. It's just alwasy 0% for a summary task.
For example:
NAME Phys % comp
===================================
RES02DEF 0%
--230kV oil 50%
--Proj mgmt 100%
--cable design 100%
--System Plan 100%
--Project Plan 25%
RES02DEF is the summary task, but I cannot edit the Physical % complete
field (like I can for its children), AND it's set to 0%, no matter what the
values of its children.
(1) Why can't I change it?
(2) And if it can't be changed, why doesn't it do something useful, like
roll up??
(Or is there something special I should do to make it roll up? I've tried
hitting the "calculate now" button, but it doesn't make a difference.)
Thanks,
Kris R.