Tanzim Akhtar
Hello,
I am using Project Server 2010 and trying a very simple formula in PWA, creating Project field type Text:
[% Complete] - [Physical % Complete]
However, it is not getting the correct result. It is calculating as if Physical % Complete is 0 (zero) and giving me the result which is obviously % Complete.
Hence I tried the following formula [Physical % Complete] i.e. just this field. The result shows is 0 (zero).
The above mentioned does not have any problem while done in Project Professional 2010 i.e. it shows appropriate calculated result.
What is wrong?
Thank you
I am using Project Server 2010 and trying a very simple formula in PWA, creating Project field type Text:
[% Complete] - [Physical % Complete]
However, it is not getting the correct result. It is calculating as if Physical % Complete is 0 (zero) and giving me the result which is obviously % Complete.
Hence I tried the following formula [Physical % Complete] i.e. just this field. The result shows is 0 (zero).
The above mentioned does not have any problem while done in Project Professional 2010 i.e. it shows appropriate calculated result.
What is wrong?
Thank you