Hello,
I have already created my project plan, have saved my baseline, and am
tracking to my baseline. My client now wants me to show the physical %
complete summary rollup%, but my understaning is that I have to:
a) set resources to all tasks
b) set all tasks to EV method of physical % complete
c) save a baseline
I am fine with a & b, but not fine with saving a new baseline. Is their any
way this summary roll-up data can be shown without saving a new baseline? I
don't want to loose what I am tracking against...
Many thanks,
Laurie
I have already created my project plan, have saved my baseline, and am
tracking to my baseline. My client now wants me to show the physical %
complete summary rollup%, but my understaning is that I have to:
a) set resources to all tasks
b) set all tasks to EV method of physical % complete
c) save a baseline
I am fine with a & b, but not fine with saving a new baseline. Is their any
way this summary roll-up data can be shown without saving a new baseline? I
don't want to loose what I am tracking against...
Many thanks,
Laurie