N
Nathalie
Hi,
I have several questions in relation to % Physical Complete and advancement
of my project.
I have several activities in a project with summary tasks. When I enter
manually the % Physical complete, The summary % is still at 0%, it is not
calculated. All my tasks are with the earned value method of % Physical
complete and I also set in the options/calculation to earned value.
Second question: I would like to compare my actual advancement with the
planned advancement. % work complete shows my actual advancement. What could
be the planned advancement? Do I have to create a new field representing this
notion? I think that the planned advancement could be represented by
BCWS/total cost.
I noticed that if I update my status date, the % complete is automatically
calculated.
If I modify the % work complete, it affects my % complete and my actual
duration, so it is like my status date is changed. How could I keep the same
% complete even if I change my % work completed?
thanks
Nathalie
I have several questions in relation to % Physical Complete and advancement
of my project.
I have several activities in a project with summary tasks. When I enter
manually the % Physical complete, The summary % is still at 0%, it is not
calculated. All my tasks are with the earned value method of % Physical
complete and I also set in the options/calculation to earned value.
Second question: I would like to compare my actual advancement with the
planned advancement. % work complete shows my actual advancement. What could
be the planned advancement? Do I have to create a new field representing this
notion? I think that the planned advancement could be represented by
BCWS/total cost.
I noticed that if I update my status date, the % complete is automatically
calculated.
If I modify the % work complete, it affects my % complete and my actual
duration, so it is like my status date is changed. How could I keep the same
% complete even if I change my % work completed?
thanks
Nathalie