Hi,

I am tracking project using physical % complete. But is there any way
to show % physical complete on Gantt Chart view. or can we see in
tracking gantt chart view?

Please let me know.

Thanks in advance.
 
R

Rob Schneider

Nilu said:
Hi,

I am tracking project using physical % complete. But is there any way
to show % physical complete on Gantt Chart view. or can we see in
tracking gantt chart view?

Please let me know.

Thanks in advance.

Take a look at the Gantt Chart Wizard (on the Format Menu), and on one
of the screens you'll see "Custom Task Information". From there it
should clear.
 