Physical % Complete

G

Guest

Hi all,

Is it possible to roll up the Physical % Complete for all
Tasks? I can not make it to work? Maybe it is not
supposted to?

Thanks,
/// Atilla
 
R

Rod Gill

Hi,

What version of Project and in what view?

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
G

Gérard Ducouret

Hello Atilla,
The Physical % Complete is used to alter the calculation of the BCWP. So it
doesn't roll up on summaries.
But you can use un Numberx field with a formula which will pick up its
value, and in the Customize Fields dialog you can check the Rollup option
button.
Hope this helps,

Gérard Ducouret
 
G

Guest

Thanks Gerard,

I will try.
/// Atilla
-----Original Message-----
Hello Atilla,
The Physical % Complete is used to alter the calculation of the BCWP. So it
doesn't roll up on summaries.
But you can use un Numberx field with a formula which will pick up its
value, and in the Customize Fields dialog you can check the Rollup option
button.
Hope this helps,

Gérard Ducouret

<[email protected]> a écrit dans le message de



.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top