K
karishma
hi
in my project, I wont to show work completed till date. as % complete and %
work complete gives the results dependent on duratin and task's work
respectively. so i am using physical % complete. i have entered the value for
subtasks for Physical % complete, but the value for the summary task is not
updatinf, it gives the 0%.
i hope my doubt is clear.
can any one help me on this issue.
Thanks in advance
in my project, I wont to show work completed till date. as % complete and %
work complete gives the results dependent on duratin and task's work
respectively. so i am using physical % complete. i have entered the value for
subtasks for Physical % complete, but the value for the summary task is not
updatinf, it gives the 0%.
i hope my doubt is clear.
can any one help me on this issue.
Thanks in advance