Physical Percent (%) Complete field

S

Sean

Physical Percent (%) Complete field is not letting me manually enter a
percentage for summary tasks
 
J

Jan De Messemaeker

Hi,

Most summary task fields are calculated and hence not available for data
entry.
HTH
 
J

Joe

Think about what you are asking Project to do. You want to manually update a
summary line and have Project "guess" what the Physical Percent (%) Complete
is for the individual task within that summary task. Does this make sense?
Are you sure this is what you really want? Suppose you have 5 tasks under a
summary task. If you could update the summary task to 50% complete, how will
Project know what the percentage complete of each individual task is? You
can't assume they are all 50% complete. So the short answer is you can't
update the summary line because it is designed that way.

HTH
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top