I've tried your scenario with a slight change and am seeing data
calculated at the project summary task line and summary line mostly
consistent with duration information.
For example:
Phase 1 - Summary - Duration 75d
Task 1 - subtask - duration 20d - calculated by entering 160 hrs
of work
Task 2 - subtask - duration 25d - calculated by entering 200 hrs
of work
Task 3 - subtask - duration 30d - calculated by entering 240 hrs
of work
Phase 2 - Summary - Duration 150d
Task 4 - subtask - duration 75d - 600 hours of work
Task 5 - subtask - duration 75d - 600 hours of work
All subtasks linked F to S
If I mark task 1 100% physically complete, the Phase 1 summary updates
to 27% which is correct for 20d out of 75d complete. The Project
summary task updates to 9% which is correct (given rounding) for 20d
out of 225d complete.
If I mark task 2 50% complete, the Phase 1 summary tasks updates to
43% which is correct for 32.5 days out of 75d complete. The project
summary task updates to 14% which is 32.5/225.
I am not seeing any recalculation of Physical % complete from entering
actual work.
I am using Project 2003 SP-3.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project