Pivot Tables and Assignment Timephased data

J

JP

When I use the Assignment Timephased data in a pivot table (using PS07), I've
found that the data displayed is approximately 2 days behind what has
actually been updated by resources.

In the pivot table, I'm viewing actual work by resources, filtered by the
days of the current week.
I've approved the task updates for the current day, yet the actual hours in
the updates will not show up in the pivot table until 2 days later.

Any idea as to why this data is not accurate to the current time?
 
P

Paul Conroy

Check the date range of your cube build settings and when the cube was last
built.
 