plan updates and reporting methods

L

lynne baker

Hi all
We're running PWA and 2002
I have a PM who updates her plans regularly, but not every day.
If she doesn't update the plan on the exact day that that particular
task is scheduled to finish when she does update it she gets a message
informing her of a scheduling conflict and the subsequent tasks are
moved accordingly - even if the task has been completed on time.
We have opted for the reporting option of "actual work done and work
remaining" and that the team members should report their hours worked
every day.
Given that it's not always possible to update the plan every day owing
to meetings, off site visits etc, what is the best way to update the
plan without having the tasks moved.

Many thanks


lynne
 