S
Sergio
Hi,
The usual working time for our resources is M-F 9-18.
We have seted up our enterprise calendar acountng for national holidays,
religious holidays, etc. There are some exceptions thou.
We have tasks in some projects that MUST be performed in enterprise non
working time.
Is there any way (via permissions, etc) for a user to modify its resources
calendar to handle this exceptions or this is only possible for the
administrator?
Thanks,
Sergio
The usual working time for our resources is M-F 9-18.
We have seted up our enterprise calendar acountng for national holidays,
religious holidays, etc. There are some exceptions thou.
We have tasks in some projects that MUST be performed in enterprise non
working time.
Is there any way (via permissions, etc) for a user to modify its resources
calendar to handle this exceptions or this is only possible for the
administrator?
Thanks,
Sergio