nataly
We have a timetracking requirement for project server deployment, meaning
that team members shall report their actuals through web interface.
Once people entered their actual that doesnt correspond to planned, server
re-calculating task values - task's start day, duration, % people are
assigned to the tals and so on.
Is it a way to separate Planned from Actual, to prevent changes to the plan
while alloving resorces to report their actuals?
that team members shall report their actuals through web interface.
Once people entered their actual that doesnt correspond to planned, server
re-calculating task values - task's start day, duration, % people are
assigned to the tals and so on.
Is it a way to separate Planned from Actual, to prevent changes to the plan
while alloving resorces to report their actuals?